A PHP Error was encountered

Severity: Notice

Message: Undefined property: stdClass::$access_token

Filename: models/Jssdk.php

Line Number: 101

Backtrace:

File: /data/www/website/www_iccsino_com_cn/application/models/Jssdk.php
Line: 101
Function: _error_handler

File: /data/www/website/www_iccsino_com_cn/application/models/Jssdk.php
Line: 78
Function: getAccessToken

File: /data/www/website/www_iccsino_com_cn/application/models/Jssdk.php
Line: 44
Function: getJsApiTicket

File: /data/www/website/www_iccsino_com_cn/application/controllers/Welcome.php
Line: 226
Function: getSignPackage

File: /data/www/website/www_iccsino_com_cn/index.php
Line: 315
Function: require_once

A PHP Error was encountered

Severity: Notice

Message: Undefined property: stdClass::$ticket

Filename: models/Jssdk.php

Line Number: 81

Backtrace:

File: /data/www/website/www_iccsino_com_cn/application/models/Jssdk.php
Line: 81
Function: _error_handler

File: /data/www/website/www_iccsino_com_cn/application/models/Jssdk.php
Line: 44
Function: getJsApiTicket

File: /data/www/website/www_iccsino_com_cn/application/controllers/Welcome.php
Line: 226
Function: getSignPackage

File: /data/www/website/www_iccsino_com_cn/index.php
Line: 315
Function: require_once

超百亿!得壹能源锂离子动力电池项目二期明年4月投产

超百亿!得壹能源锂离子动力电池项目二期明年4月投产

电池网 4624 2025-02-18 14:46:50

据“枞阳经开区”发布消息,2月17日,得壹能源锂离子动力电池二期主厂房桩基正式施工,项目进入实质性建设阶段。
 
据介绍,得壹能源锂离子动力电池项目二期规划建设4条超级电芯生产线、实现年产能20GWh,总建筑面积约23万平方米,计划2025年6月底完成厂房竣工验收、7月初设备进场并安装调试、9月28日产线通线,2026年4月项目建成投产。
 
资料显示,得壹能源锂离子动力电池项目位于安徽铜陵枞阳开发区桥港园区,于2022年1月签约,总投资100.04亿元,是奇瑞汽车旗下动力电池产业化的重要项目。其中,项目二期占地约670亩,总投资约80亿元,主要产品为方形磷酸铁锂电池。
鑫椤报告

研究报告:
● 《锂电池产业链周报》
● 《鑫椤前瞻-全球锂电池产业链内参月度报告》
● 《两轮车及低速车市场月度报告》
● 《全球锂电池及新能源汽车品牌数据报告》
● 《鑫椤资讯炭素周刊》
● 《中国炭素市场月度报告》
年报系列:
● 《磷酸铁锂产业链价值研究报告》
● 《动力锂离子电池行业研究年度报告》
● 《全球三元材料产业链价值研究报告》
● 《中国钴酸锂产业链价值研究报告》
● 《全球锂电池及下游应用市场年度调研报告》
● 《全球电动两轮车及低速车市场报告》
● 《锂电负极材料产业链剖析》
● 《天然石墨及应用市场年度报告》
● 《中国针状焦及应用市场年度报告》
数据库:
● 基础库及其他定制数据需求
订制系列:
● 竞争企业调研
● 用户市场调研
● 供需市场调研
● 战略调研报告
● 成本分析报告
● 市场预测报告